Fixed price, unit rates or cost-plus: building contract types in Turkey
Two quotes for the same house can rest on different contract types, and each leaves the risk with a different party. Lump-sum, unit-rate and cost-plus contracts explained for owners building in Fethiye.
Architect Okan Çakal

Two quotes for the same villa can end on almost the same figure and still be very different offers. If one is a fixed price and the other is based on unit rates, you are really comparing two different agreements. The contract type decides who pays for the uncertainties that every build throws up: more excavation than expected, material prices that move, a decision made late. Below we compare the three main contract types you are likely to meet when building your own home on your own plot in Fethiye, from our experience on site and from the owner's side of the table. This is general information, not legal advice; before you sign, have the contract reviewed by a lawyer, and if it is drafted in Turkish, get an independent translation first.
1. What a contract type really decides: three kinds of risk
- Quantity risk: how much work there will turn out to be. Rock in the excavation, a retaining wall longer than drawn, rotten plaster revealed when an old building is stripped.
- Price risk: material and labour prices changing during the build.
- Scope risk: uncertainty over what is included; items that are not on the drawings but that everyone assumed would be done.
Each contract type shares these risks differently. A contractor prices in the risk it carries; an owner manages the risk it keeps through closer follow-up and a budget margin.
2. Fixed price (lump sum): one price for a defined job
A total price for the whole job, agreed at the start. Most turnkey contracts are built this way. Within the defined scope, any difference in quantities is the contractor's problem.
- For the owner: the budget is known from day one, which makes financing simple. Progress payments (hakediş, the stage payments used in Turkish contracts) are released when defined stages are completed, not on measurement.
- Watch out for: everything depends on a well-defined scope. If the construction drawings, materials schedule or list of exclusions are thin, arguments about "is this included?" are inevitable. A contractor adds a margin for every unclear item, and an undefined material specification naturally drifts towards the cheapest option.
- Suits: a new villa with complete drawings and materials decided, or an interior renovation with a clear scope.
3. Unit rates (re-measurement): actual quantities at agreed rates
The job is broken down into items (cubic metres of concrete, square metres of plaster or tiling, metres of pipe) and each item's rate is fixed in the contract. You pay for the quantities actually built and measured; the total in the quote is only an estimate.
- For the owner: fair where quantities can't be known in advance, because nobody pays upfront for the unknown. Changes are easy to price using the agreed rates.
- Watch out for: the final cost is not known until the job is finished. If the contract doesn't say how measurement works (which drawings, whether door and window openings are deducted) and how a rate is set for an item not on the list, disputes move to the measurement sheets.
- Suits: groundworks and retaining walls on a sloping plot, renovations of older buildings, and work where the scope is clear but the quantities are not.
The clearer the plan, the more accurately items and quantities can be read from it.

4. Cost-plus: documented cost plus a contractor's fee
You pay the documented actual cost of materials and labour, plus a fee covering the contractor's management and profit. The fee can be a fixed sum or linked to cost.
- For the owner: the most transparent model. There is no need for the contractor to price in uncertainty, work can start before every decision is made, and it adapts most easily to change.
- Watch out for: the total is open-ended. If the fee rises with cost, the incentive to keep costs down weakens, so a fixed fee, a target budget and approval thresholds for spending are usually combined. Invoices, delivery notes and labour timesheets must be kept in order, and the contract should say who benefits from supplier discounts and refunds. The time you spend checking all this, possibly from abroad, is part of the real cost.
- Suits: renovations whose scope will become clear stage by stage, and jobs where you can follow the paperwork closely and trust is high on both sides.
The contract type doesn't set the price of the job; it decides who pays for the uncertainty.
5. Hybrid arrangements are common
In practice, mixed approaches are as common as the pure types:
- Fixed price for the main structure, unit rates for excavation and retaining walls.
- A fixed-price contract with provisional sums for items not yet chosen, such as the kitchen, sanitaryware or light fittings; the contract states how the difference is settled if your choice comes in under or over the allowance.
- Cost-plus with a ceiling or target budget.
A hybrid prices each part of the work in the way that suits it, provided the contract clearly states which items fall under which model.
6. Clauses every contract type needs
Some clauses are needed whatever the model; we go through them in detail in our article on turnkey construction contracts:
- Scope and attachments: drawings, materials schedule, exclusions.
- Material specification: type and grade, and how an equivalent is defined.
- Work programme: stages and milestones.
- Stage payments: for a fixed price, a definition of each completed stage; for unit rates, signed measurement records; for cost-plus, the invoice file. How stages are checked is covered in our article on checks at each construction stage.
- Price adjustment clause: what happens if material prices change.
- Change procedure: written requests, with cost and programme effects agreed in writing before approval.
- Handover and post-handover responsibilities: the snagging list and how defects are reported and put right.
7. Why an itemised quote matters with any model
Seeing the quote item by item, with quantities and material grades, shows where the risk sits whichever model you choose. We prepare our quotes item by item and write scope, material grade, work programme and payment stages into the contract separately. When the same team that draws the project also builds it, the drawings and the quote come from one source; we discuss the pros and cons of that arrangement in architect or contractor?
How we take a house or villa from quote to handover in Fethiye is explained on our construction in Fethiye page.
Frequently asked questions
Which contract type suits me if I live abroad during the build?
A fixed price with a fully defined scope needs the least day-to-day involvement, while cost-plus asks for the closest scrutiny of invoices. Whichever you choose, tie payments to completed, checked stages rather than dates.
Does a fixed price mean the price can never change?
It is fixed for the defined scope, but out-of-scope changes and the contract's price adjustment clause can affect it. Both should be written clearly before signing.
What is a provisional sum?
An allowance in a fixed-price contract for something not yet chosen, such as the kitchen or light fittings. The contract should say how the difference is settled when the actual choice costs more or less.